Design, manufacturing, supply, transport, erection, tests and commissioning of the main and auxiliary Electromechanical Equipment (Turnkey package of the electromechanical part of the Project):
- Francis Turbine, vertical shaft, Governor with Oil-hydraulic Unit, Three-phase Synchronous Generator, Excitation System, Butterfly Valve, SCADA, Electrical and Control Equipment, Tool set and Erection accessories.
- Grounding network in the house, and Grounding panels for the Generating Unit, Lifting mechanisms (Hoist with its travel beam), Fire protection System (detection, alarm and extinguishers).
- Integral Engineering of Electromechanical equipping.
- Direction and Coordination.
- Progress Control and Quality Management.
- Electrical and Mechanical Auxiliary Equipment.
- Erection and Commissioning.
- Supply and Operation of the equipment for the Transmission Lines and Substation of the Interconnection to the National Electric Network of the Republic of Panama.